Metro rail work gets into gear

Metro rail work gets into gear

Shawdesh desk:

The ongoing metro rail projects in the capital are gradually gaining momentum, thereby returning to their pre-Covid-19 state in line with the return of foreigners that left the country during the virus outbreak.

Even though some important mega projects were running in a limited scale during the lockdown period, the work of metro rail projects was put nearly to a halt as Japanese experts, contractors and workers left for their country.

Recently, the work started again as the Japanese project people started joining their project work. Apart from Mass Rapid Transit (MRT-6) stretching from Uttara to Motijheel, work of two smaller links is also going on.

 

“The work of time-bound MRT Line-6 is going on in full swing, while work for detailed designing of MRT Line-1 from Kamalapur to Airport and from Notun Bazar to Pitolganj depot is also under way,” commented an official of Dhaka Mass Transit Company Ltd (DMTCL).

The consulting firm appointed for detailed design, tender assistance and construction supervision for MRT Line-5 northern route started work from 12 August 2020, DMTCL officials said.

The appointment of consulting firm for MRT Line-5 southern route is at the final stage, they added.

Besides, the appointed consultant for MRT Line-2, to be built on G2G PPP basis, started Full Scale Study (FSS) from 15 September this year, and construction of another route MRT Line-4 from Kamlapur to Narayanganj is under process.

In the current fiscal’s ADP, the government allocated a total of Tk72.44 billion, including Tk55.43 billion for MRT-6.

The total budget of these projects is Tk1.17 trillion, including Tk219.85 billion for mass rapid transit (MRT) line-6.

 

The fast-track report of Economic Relations Division’s (ERD) suggests that a Tk5.54 billion has so far been spent on the metro rail projects in the first quarter of this current fiscal from the current ADP allocation.

Cumulative expenditure from the beginning stood at Tk124.33 billion.

The Uttara-Motijheel MRT-6 is being implemented at an estimated cost of Tk219.85 during July 2012 to June 2024 period. In FY21, ADP allocation for the scheme is Tk55.43 billion.

Of the yearly ADP allocation, over Tk3.37 billion has been spent in the first quarter. Cumulative expenditure of the project, also called Dhaka metro rail, stood at over Tk117.35 billion in the first quarter.

ERD progress report suggests that the MRT Line-6 saw an overall progress of 53.37 percent in the first quarter of FY21.

Public works of the first phase of the route from Uttara to Agargaon advanced 76.87 percent in the first four months of FY21 and that of Agargaon-Motijheel portion 45.51 percent, according DMTCL data.

Procurement of electrical and mechanical system, rolling stock and depot equipment progressed 39.73 percent.

Social study for extension of 1.16km from Motijheel to Kamalapur in line with the Prime Minister’s directive is at the final stage, according to DMTCL officials.

The MRT Line-1 is being implemented at an estimated cost of Tk525.70 billion to complete it by December 2026. Of the 31.24km route, 19.87km will go underground and 11.36km will be elevated.

The government allocated Tk5.91 billion for the project, of which Tk1.47 billion has been spent in the first quarter, according to ERD’s report. Cumulative expenditure from the beginning stood at Tk3.47 billion to post 0.66 percent financial progress so far.

20km MRT Line-5 (northern route) is being implemented from Hemayetpur to Vatara via Mirpur at a cost of Tk412.39 billion from September 2019 to December 2028 period.

A Tk8 billion was allocated this year against this project and Tk532.5 million was spent from ADP allocation in the first quarter and its cumulative cost has been Tk725.7 million. So far, its overall progress was 0.18 percent.

Besides these projects, feasibility studies are being done for MRT Line-5 (southern route) which progressed 0.08 percent so far.

Share This News

Leave a Reply

Your email address will not be published. Required fields are marked *

© All rights reserved © 2019 shawdeshnews.Com
Design & Developed BY ThemesBazar.Com
themebashawdesh4547877