Coal lifting from Barapukuria mine stops, exploration from new face Nov

Coal lifting from Barapukuria mine stops, exploration from new face Nov

Shawdesh desk:

Lifting of coal from Barapukuria mine located in Parbotipur upazila of Dinajpur has stopped  in 1,113 number coal face due to  finishing of reserve.

Exploration of coal halted around 6:00pm on Tuesday, competent source said.

Abu Bakar Siddique, chief engineer of Barapukuria 525 thermal power plant, said production of electricity has reduced resulting from the incident.

 

Sources said a total of 3.75 lakh metric ton coal was lifted from 1,113 coal face. Now, coal will be lifted from new face where 2.16 lakh metric ton coal is stored.

Authorities concerned said production equipment used in 1113 number face will be   transferred to1412 face. Machines are being installed in the new face which is expected to go to production in the first week of November.

Share This News

Leave a Reply

Your email address will not be published. Required fields are marked *

© All rights reserved © 2019 shawdeshnews.Com
Design & Developed BY ThemesBazar.Com
themebashawdesh4547877